The administrative committee overseeing the university hospital visited the hospital’s site on Sunday, September 13, 2020, and discussed with the executing company the hospital’s design, completion rates, and the possibility of increasing the number of operating theaters. The committee indicated that the completion rates reached about 39.9%, which is very close to the planned 40%, and that it found great eagerness on the part of the company director and the resident engineer department to complete the work within the time limit set in 2022 and it was decided to continue visits and communication by the supervising committee and the implementing company.